Road_Construction_Sign

As I continue to speak with constituents in the district, everyone wants to know about roads! I’m pleased that most see the improvements in our area; but also understand their frustration with our state road system.

Below is an update to the report provided last August of improvements in our area:

SC-6 @ Salem Church Road Intersection Improvement
Project is now complete.

S-40-216: Lowman Home Barn Road
Project is now complete.

S-40-296 – A.J. Amick Road
Project is now complete.

S-40-620: Captain Lowman Road
This road is under contract for single treatment – Contract ID 5190090. C. R. Jackson is the prime contractor. No work has been performed on this road to date. We anticipate that C. R. Jackson will begin full depth patching in May 2016 and follow up with surface treatment shortly after patching is complete. The project has a completion date of September 30, 2016.

US-76 @ Johnson Marina Road Intersection Improvement

This is an intersection improvement project that will provide turn lanes on both US-76 and Johnson Marina Road. Traffic Engineering is currently developing plans for the project. They have indicated issues with both right of way and railroad at this location. The project is tentatively scheduled to be let September 2016.

Richland County Penny Project – Kennerly Road at Coogler Road
This is a Richland County Penny Project begin administered by ICA Engineering. Per my discussion with Project Manager Jennifer Bragg, the scope of the project is to install a roundabout at this intersection. It is one of six intersections included in a Design Build contract. The contract was awarded to C. R. Jackson with a window for completion in Spring 2017 of all intersections. For more information, you may contact Project Manager Jennifer Bragg at (803) 726-6146 or Richland County Transportation Director Rob Perry at (803) 576-1526.

Richland County CTC Resurfacing
Shadowood Drive (S-1680) is complete. West Shady Grove Road (S-612) needs additional full depth patching and then will be resurfaced. Water Garden Court (S-1708) is complete. The contract completion date is October 31, 2015. Lane is in Liquidated Damages at this time for not completing the project by the completion date.

Amicks Ferry Safety Improvement
This project was awarded to Lane Construction in September 2015. This project involves select clearing, widening the pavement ~1’ on each side, resurfacing, pavement markings, and guardrail. Clearing work is expected to begin mid to late April. The project is expected to be completed by Fall 2016.

St. Peters Church Road Safety Improvement
Tentative July 2016 Letting. This project involves moving the ditches back, widening the road ~2’ on each side, resurfacing, pavement markings, and guardrail.

Murray Lindler Road @ Old Lexington Road Roundabout
Tentative November 2016 letting.

OTHER COMPLETED PROJECTS

Firetower Road Bridge Replacements
Both of the bridges on Firetower Road have been replaced with SCDOT crews and the road has been reopened.

PROJECTS ADDED TO THE LIST

S-40-621: Trillie Lane
This road is under contract for full depth reclamation and asphalt surface triple treatment. The completion date is November 30, 2016.

S-40-2265: Silver Point Road
This road is under contract for full depth reclamation and asphalt surface triple treatment. The completion date is November 30, 2016.

S-40-940: Peace Haven Road
This road is under contract for full depth reclamation and asphalt surfacing. The completion date is October 31, 2016.

S-40-1403: Three Dog Road
This road is under contract for full depth reclamation and asphalt surfacing. The completion date is October 31, 2016.

I-26 and Interstate Pavement Preservation
Interstate Preservation: I-26 from MP 100.8 to MP 107.7 in Richland and Lexington Counties. Anticipated to be in the April 12, 2016 Letting with a June 30, 2018 Contract Completion Date

I-126 Interstate Pavement Preservation
Interstate Preservation: I-126 from MP 0.00 to MP 3.68 in Richland County. Anticipated to be in the April 12, 2016 Letting with a June 30, 2018 Contract Completion Date

I-26 Widening
FROM EXIT 101 (US 176) HEADING WEST TO BE DETERMINED – RICHLAND, LEXINGTON, AND NEWBERRY COUNTIES
The project includes widening of I-26 from MM 101 (US 176, Exit 101- Irmo) heading west on I-26 with the western termini to be determined. Project includes widening I-26 from 4 to 6 lanes for approximately 16 miles; overpass bridge replacements at S-58 (Koon Road), S-80 (Shady Grove Road), S-234 (Mt. Vernon Church Road), S-405 (Old Hilton Road), and S-49 (Peak Street); and jacking/rehabilitating overpass bridges at S-39 (Peak Road) and S-167 (Parr Road). Project is scheduled for 2018.

Other notable projects in the Chapin area include:
• Lexington Avenue Enhancement (Landscaping) Project for the Town of Chapin