Search Results for: malfunction

The fix for Malfunction Junction (and more) coming our way

We’ve been seeing road improvements in the area for years, and soon, the biggest improvement of them all is coming our way. Not just the fix for Malfunction Junction, improvements on out towards the Peak, Little Mountain and Newberry area.

From The State

Overshadowed by the S.C. Department of Transportation’s massive $1.5 billion effort to untangle Columbia’s notorious “Malfunction Junction” interchange at I-20, I-26 and I-126 is another big highway improvement project.

Beginning in 2020 and ending fours years later, workers will widen I-26 for 16 miles from Broad River Road northwest to Little Mountain. That widening project would link with the Malfunction Junction project — officially called Carolina Crossroads — at Exit 101, Broad River Road.

Both projects are expected to begin in 2020.

Although public hearings have been held on the extended I-26 widening project, many folks who regularly roll up to Greenville and Spartanburg from the capital city, or vice versa, probably don’t know that their trek is going to be more difficult for a long time before it gets a lot better.

“We’re flying under the radar a little,” project manager Michael Hood said.

The $530 million project begins at Exit 101, which is U.S. 176., in Irmo. That’s where the Malfunction Junction project will end.

The existing two lanes on each side of the highway will be widened to four lanes for a total eight-lane section of highway to Broad River Road, which is the Peak exit.

The road will be widened to six lanes for the remaining 12 miles from U.S. 176 to S.C. 202 at Little Mountain. Future plans envision a widened highway all the way to Newberry.

Read more here

A new name; but more importantly a new look

“Carolina Crossroads” – by now you probably know that’s the “new name” given to what we all call “Malfuction Junction”. For months, many of you have been to the forums and meetings to provide your input and help make everyone’s morning commute better. Thank you for being so involved!

It’s the number one priority in our state for the SC Department of Transportation and each day we move closer to a smoother commute.

I’ve written before about this major improvement coming for our area (and state) and want to be sure you are kept informed throughout the process.

If you aren’t currently receiving updates from SCDOT, click here to sign up!

Lane closures this weekend: Carolina Crossroads

Long way to go on the proposed fix for “Malfunction Junction” but this weekend you will begin to SEE work that will ultimately result in less headaches and congestion that we face each and every day on the commute downtown!

The Jan 28-Feb 1 schedule for nighttime lane closures scheduled on portions on I-126 and I-26 for drilling operations and soil testing associated with the Carolina Crossroads project:

Please note: This is standard procedure on many projects as part of the preliminary engineering process. Construction is not expected to begin until 2019. For more information, please visit http://www.scdotcarolinacrossroads.com/

UPDATE: several road improvements

w20-7a

Hopefully you’ve noticed improvements all around our community in the past several months! You will continue to see more in the months and years ahead!

When we return to session in January, the General Assembly will continue to address our infrastructure needs as this is vital not only to our way of life; but also the future of our state’s economy (aka jobs, jobs, jobs)

Thanks for bringing several of these needs to my attention. Thank you SCDOT for always being willing to listen and perform the studies needed to find solutions and improve safety!

By the way, there are 3 meetings next month that may be of interest to you:

October 4th (5pm-7pm) Seven Oaks Elementary – Carolina Crossroads (aka Malfunction Junction)
October 11th (5pm-7pm) Chapin High School – I 26 Widening Project ranging from est Exit 85 to Exit 101
October 13th (5pm-7pm) Chapin Middle School – same as above

** RECENTLY COMPLETED PROJECTS IN OUR AREA **

Richland County CTC Resurfacing
West Shady Grove Road (S-40-612).

S-40-940: Peace Haven Road
Completed except for permanent pavement markings.

S-40-1403: Three Dog Road
Completed except for permanent pavement markings.

S-40-620: Captain Lowman Road

** ACTIVE PROJECTS **

S-40-621: Trillie Lane
This road is under contract for full-depth reclamation and asphalt surface triple treatment. The completion date is November 30, 2016. RCE is Chris Kelly, can be contacted at 786-0706 regarding this project.

S-40-2265: Silver Point Road
This road is under contract for full-depth reclamation and asphalt surface triple treatment. The completion date is November 30, 2016. RCE is Chris Kelly, can be contacted at 786-0706 regarding this project.

** RICHLAND COUNTY PENNY PROJECT **

Kennerly Road at Coogler Road
This is a Richland County Penny Project being administered by ICA Engineering. Per my discussion with Project Manager Jennifer Bragg, the scope of the project is to install a roundabout at this intersection. It is one of six intersections included in a Design Build contract. The contract was awarded to C. R. Jackson and work started mid-August. The work on this project is expected to be completed in Spring of 2017. For more information, you may contact Project Manager Jennifer Bragg at (803) 726-6146 or Richland County Transportation Director Rob Perry at (803) 576-1526.

Widening Broad River Road
This is a Richland County Penny Project being administered by ICA Engineering. The general scope of this project is widening of Broad River Road from North Royal Tower Road to beyond I-26. The construction work is currently planned to begin in 2020. For more information, you may contact Richland County Transportation Director Rob Perry at (803) 576-1526.

I-26 Interstate Pavement Preservation
Interstate Preservation: I-26 from MP 100.8 to MP 107.7 in Richland and Lexington Counties. This project was in the July 12, 2016 Letting with a November 30, 2018 Contract Completion Date. Anticipated start is Spring 2017. Project is being managed by CEI Consultant – Infrastructure and Consulting Engineers. Point of contact is Jim Cravens, can be contacted at 822-0333 regarding this project.

I-126 Interstate Pavement Preservation
Interstate Preservation: I-126 from MP 0.00 to MP 3.68 in Richland County. This project was in the July 12, 2016 Letting with a November 30, 2018 Contract Completion Date. Anticipated start is Spring 2017. Project is being managed by CEI Consultant – Infrastructure and Consulting Engineers. Point of contact is Jim Cravens, can be contacted at 822-0333 regarding this project.

** 2016 Richland CTC Resurfacing Program **

Treatment: Resurface
Proposed Let Date: June 14, 2016
Completion Date: November 30, 2017
• Firetower Rd. – Kennerly Rd. to Western Ln.
• Scotts Hill Rd. – Hiller Rd. to Dead End.
• Owenswood Ln. – Western Ln. to Dead End.
• South Hampton Dr. – Koon Rd. to Davenport Dr.
• Davenport Dr. – Sutton Way to South Hampton Dr.
• Western Ln. – Broad River Rd. to 0.85 miles North of US 76.
Resident Construction Engineer: Chris Kelly 803 786-0706

** 2017 Federal Aid Preservation Program **
Treatment: Full Depth Patching (6211)
Proposed Let Date: September 13, 2016
Completion Date: TBD
• Chapin Rd. – Newberry Co. Line to Richland Co. Line.
Resident Construction Engineer: Joey McIntyre 803 359-4672

Treatment: PMST / Microsurfacing
Proposed Let Date: March 14, 2017
Completion Date: TBD
• Broad River Rd. – Newberry Co. Line to Broad River Rd.
Resident Construction Engineer: TBD

Treatment: Crack Seal
Proposed Let Date: March 14, 2017
Completion Date: TBD
• Dreher Shoals Rd. (SC 6) – US 76 to Lexington Co. Line.
• Dutch Fork Rd. (US 76) – Lexington Co. Line to 0.25 miles West of Gates Rd.

Resident Construction Engineer: TBD

** 2017 Federal Aid Rehab. Program **
Treatment: Resurface
Proposed Let Date: January 10, 2017
Completion Date: TBD
• N. Woodrow St. – Broad River Rd. to N. Royal Tower Rd.
Resident Construction Engineer: TBD

Treatment: Full Depth Reclamation
Proposed Let Date: TBD
Completion Date: TBD
• Ray Stoudemayer Rd. – Broad River Rd. to Newberry Co. Line
• Freshly Mill Rd. – Broad River Rd. to John Chapman Rd.

Resident Construction Engineer: TBD

** 2017 Non-Federal Aid Rehab. Program **
Treatment: Resurface
Proposed Let Date: September 13, 2016
Completion Date: TBD
• Dan Comalander Rd. – Broad River Rd. to Lexington Co. Line.
• Page Derrick Rd. – Kennerly Rd. to Shady Grove Rd.
• Eleazer Rd. – Shady Grove Rd. to Kennerly Rd.
• Point Dehaven Rd. – Richard Franklin Rd. to Local Rd.
• Rucker Rd. – Johnson Marina Rd. to Local Rd.
• Old Rd. – Richard Franklin Rd. to Old Rd.
• Creekwood Rd. – Old Rd. to Dead End.
• Circle Dr. – Richard Franklin Rd. to Richard Franklin Rd.
• Lazy Cove Ln. – Silver Point Rd. to Dead End.
• Gates Rd. – Dutch Fork Rd. to Wise Rd.

Resident Construction Engineer: Paul Miller 803 786-0717

** 2017 Non-Federal Aid Preservation Program **

Treatment: Full Depth Patching
Proposed Let Date: September 13, 2016
Completion Date: TBD
• Sid Bickley Rd. – Chapin Rd. to Dead End.
• Indian Fork Rd. – Hiller Rd. to Dead End.

Resident Construction Engineer: Joey McIntyre 803 359-4672

Treatment: Chip Seal
Proposed Let Date: June 14, 2016
Completion Date: June 30, 2017
• White Rock Rd. – Mt. Vernon Church Rd. to White Rock Rd.
• White Rock Rd. – White Rock Rd. to White Rock Rd.
• Three Dog Rd. – Old Hilton Rd. to Three Dog Conn.
• Three Dog Conn. – Old Hilton to Stone Hill Rd.
• Brody Rd. – Johnson Marina Rd. to Dead End.
• Amenity Rd. – Johnson Marina Rd. to Dead End.

Resident Construction Engineer: Robert Power 803 796-9540

Treatment: Chip Seal
Proposed Let Date: October 11, 2016
Completion Date: TBD
• Willow Cove Rd. – Old Forge Rd. to Dead End.
Resident Construction Engineer: Robert Power 803 796-9540

** FUTURE PROJECTS **

US-76 @ Johnson Marina Road Intersection Improvement
This is an intersection improvement project that will provide turn lanes on both US-76 and Johnson Marina Road. Traffic Engineering is currently developing plans for the project. They have indicated issues with both right of way and railroad at this location. The project was let September 2016 and has a completion date of September 30, 2017. RCE is Joey McIntyre, can be contacted at 359-4672 regarding this project.

St. Peters Church Road Safety Improvement
Tentative December 2016 Letting. This project involves moving the ditches back, widening the road ~2’ on each side, resurfacing, pavement markings, and guardrail. RCE is Joey McIntyre, can be contacted at 359-4672 regarding this project.

Bypass Lane on US 76 at Hiller Road
SCDOT Maintenance will construct a bypass lane on the railroad side of US 76. Work is expected to be completed by the end of October.

I-26 Widening
FROM EXIT 101 (US 176) HEADING WEST TO BE DETERMINED – RICHLAND, LEXINGTON, AND NEWBERRY COUNTIES.
The project includes widening of I-26 from MM 101 (US 176, Exit 101- Irmo) heading west on I-26 with the western termini to be determined. Project includes widening I-26 from 4 to 6 lanes for approximately 16 miles; overpass bridge replacements at S-58 (Koon Road), S-80 (Shady Grove Road), S-234 (Mt. Vernon Church Road), S-405 (Old Hilton Road), and S-49 (Peak Street); and jacking/rehabilitating overpass bridges at S-39 (Peak Road) and S-167 (Parr Road). Project is scheduled for 2018.

Other notable projects in the Chapin area include:
• Lexington Avenue Enhancement (Landscaping) Project for the Town of Chapin.
• Columbia Avenue Corridor Improvement Project – this proposed project is being administered by Lexington County. A consultant has proposed several alternatives for replacing the bridge over I-26, widening Columbia Avenue, and constructing new connector roads. These alternatives have been narrowed to a preferred plan that is being further developed and will be presented for public review sometime during the Fall or Winter of 2016.